What to Expect During Your Commercial Construction Timeline
A successful commercial construction project follows a structured timeline—from pre-construction planning to permitting, site work, vertical construction, and final inspections. Understanding each phase helps Portland property owners, developers, and business operators stay on budget, reduce delays, and achieve project goals with confidence.

Introduction
When beginning a commercial construction project in Portland, it’s critical to understand the complete construction timeline—not just in terms of what comes first and last, but how long each stage typically takes and what it demands from the client, contractor, and city. Many delays and budget overruns stem from unrealistic expectations or missing pieces in early planning. At Modern NW, we approach each project with transparency and detail, walking our clients through every milestone to reduce risk and create predictability.
Whether you’re remodeling an existing space or starting from the ground up, this article outlines what to expect throughout the process—from initial planning to final inspections—based on our experience navigating Portland’s unique regulatory landscape.
Laying the Groundwork: Pre-Construction (2–6 months)
Every project begins long before a crew steps onsite. The pre-construction phase includes everything from evaluating the site to defining the scope, budget, and scheduling strategy. In Portland, this often starts with zoning review and property research, particularly for sites within design or historic overlay zones that can restrict certain design elements or add time to the approval process.
During this stage, feasibility studies assess whether the site aligns with your business goals. Architects and engineers begin developing schematic designs that guide early budgeting and allow you to make crucial decisions about layout, square footage, structural needs, and tenant requirements. Contractors like Modern NW can also step in here to assist with constructability reviews, cost modeling, and phasing strategies.
While clients often want to move quickly, skipping steps here leads to change orders and delays later. Allocating enough time for pre-construction creates clarity and alignment before any permits are submitted or materials are ordered.
Permitting in Portland: Expect 2–4+ Months of Processing
Portland’s permitting process is often the most time-intensive stage of the entire commercial construction timeline. While smaller tenant improvement projects may receive permits within 4–6 weeks, ground-up construction, change-of-use spaces, or projects in overlay zones can take several months to move through the review system.
Permit applications in Portland are submitted digitally through the DevHub portal and are reviewed by several city departments, including structural, life safety, zoning, mechanical, plumbing, and electrical. Incomplete plans or uncoordinated documents can reset timelines, so it’s crucial that all plans are fully developed, aligned, and code-compliant before submission.
Common permits include building permits, mechanical and plumbing permits, electrical permits, site development or erosion control approvals, and change-of-occupancy permits if the intended use is different from prior tenants. For example, converting a retail storefront into a clinic or restaurant often requires additional scrutiny around egress, accessibility, and sanitation.
Given the city’s staffing variability and volume of applications, it’s wise to build a 3–4 week contingency buffer into your schedule.
Site Work & Mobilization (1–3 weeks)
Once permits are in hand, the site is prepared for construction. Mobilization involves setting up temporary power, fencing, erosion control, and staging areas for equipment and materials. Crews begin by clearing the site, excavating for foundations, and installing any underground utilities or drainage systems.
Inspections often begin here as well—most notably footing and erosion control inspections. The site must meet city requirements before vertical construction can begin, and weather or access conditions can occasionally slow this process down.
Structural Framing & Building the Core (1–2 months)
With the site ready, the team begins building the physical structure. This includes forming and pouring concrete foundations, erecting structural steel or wood framing, and preparing for the roof installation. During this phase, the skeleton of the building takes shape, and major layout elements become visible.
It’s a stage where sequencing matters. Any errors in alignment or elevation at this point can cascade into future build stages. Working with an experienced general contractor ensures that inspections, shop drawings, and field conditions are all reconciled before moving forward.
Mechanical, Electrical, and Plumbing Rough-In (2–4 weeks)
Once framing is in place, subcontractors begin installing the infrastructure systems that power and regulate the space. HVAC ducts, conduit for lighting and power, data wiring, water supply lines, and gas piping are all installed during this rough-in period.
Because these systems often intersect, coordination is key. Mechanical trades must route ductwork without impeding plumbing risers. Electricians and low-voltage teams need space within wall cavities that also serve other systems. Inspections by the City of Portland must approve this rough-in work before the walls can be insulated and closed.
Delays here usually stem from scheduling conflicts between trades or missed inspection windows, so it’s crucial that the general contractor maintains tight oversight.
Interior Build-Out and Final Finishes (4–8+ weeks)
With the building enclosed and systems roughed in, the focus shifts to interior finishes. This includes drywall installation, painting, ceiling grid placement, flooring, cabinetry, and tenant-specific upgrades. Bathrooms are tiled and fitted out, break rooms take shape, and branding elements like signage or feature walls are added.
Simultaneously, the systems installed earlier are finalized—light fixtures and switches are trimmed out, plumbing fixtures are installed, HVAC units are commissioned, and thermostats or controls are tested. This stage brings the design to life and often involves the most stakeholders, including tenants, designers, and owners.
Because of the number of moving parts, final finishes tend to be where delays stack up if decisions aren’t made early or trades overlap poorly.

Final Inspections and Certificate of Occupancy (1–3 weeks)
With the work largely complete, it’s time for the final round of inspections. In Portland, this includes building, mechanical, electrical, plumbing, accessibility, and often a fire/life safety inspection. For restaurants, clinics, or childcare centers, health inspections may also be required before occupancy.
Once these inspections are passed, the city issues a Certificate of Occupancy (CO), which confirms the space is approved for its intended use. This milestone is essential for legal operation and lease enforcement and is often a requirement for tenant move-in or financing.
It’s best practice for contractors to walk the space ahead of inspections to identify small issues—like missing signage, door closers, or handrail requirements—that could hold up approval.
Turnover and Post-Construction Wrap-Up
While construction is technically finished, the project isn’t truly complete until close-out is handled. This includes final cleaning, touch-ups, removal of temporary structures, and delivery of close-out documentation like as-builts, warranties, lien waivers, and maintenance manuals.
Modern NW also supports owners and tenants during this transition—coordinating move-in logistics, training facilities teams, and addressing any punch list items that arise in the first weeks of use.
How Long Does Commercial Construction Really Take in Portland?
Project duration varies based on scope, permitting complexity, and weather—but here are general timelines for reference:
- Tenant Improvements (TI): 4–6 months
- Mid-Scale Renovation or Addition: 6–10 months
- Ground-Up Commercial Project: 10–16 months
- Medical, Institutional, or Complex Build: 12–18 months
These durations include the full cycle—from pre-construction and permitting to final occupancy—and reflect the realities of Portland’s permitting pace and seasonal construction conditions.
What Causes Timeline Delays—and How to Prevent Them
Even well-planned projects can encounter obstacles. Permitting delays, incomplete plan sets, unforeseen site conditions (such as undocumented utilities or unsuitable soil), material lead times, and tenant-driven changes are all common culprits.
The most effective way to prevent these issues is with proactive communication, early coordination, and experienced project leadership. At Modern NW, we structure every job with built-in contingencies, weekly schedule reviews, and aligned stakeholder meetings to keep things moving.
Conclusion
A commercial construction timeline involves far more than breaking ground and building up. Each phase plays a critical role in project success, and when understood clearly, the process becomes a powerful roadmap—not a source of stress.
At Modern NW, we believe transparency builds trust. That’s why we walk our clients through every milestone, from site selection to occupancy. Whether you’re planning a new office, renovating a retail shell, or expanding an existing facility, we’re here to keep your timeline efficient, your vision intact, and your investment protected.