What Is a Pay Application? The AIA G702 and G703, Line by Line
A pay application is a contractor's request for a progress payment, usually sent monthly. The payment rules come from the contract's general conditions. It shows how much of each line of work is done, adds approved change orders, subtracts retainage and what was already paid, and arrives at the amount due now. On AIA contracts it is two forms: the G703 continuation sheet, which lists every line of the schedule of values, and the G702 Application and Certificate for Payment, the one-page cover that totals it and is certified by the architect.
| G702 line | What it means |
|---|---|
| Original contract sum | The price in the signed contract |
| Net change by change orders | Approved changes added or subtracted |
| Contract sum to date | The current contract price |
| Total completed and stored to date | Work done plus materials stored, from the G703 |
| Retainage | The amount held back, on completed work and on stored material |
| Total earned less retainage | What the contractor has earned so far, net of retainage |
| Less previous certificates for payment | What earlier pay applications already approved |
| Current payment due | The amount for this period |
| Balance to finish, including retainage | What is left on the contract |
The summary lines on the AIA G702-1992 form. The G703 supplies the line-by-line numbers behind them.

Want pay applications you can check against the site? We bill line by line against a schedule of values you can walk. Licensed in Oregon (CCB #198582) and registered in Washington (L&I MODERNI888R7). Call (360) 326-2747.
How a pay application is built
It starts with the schedule of values, the list that splits the contract price into lines of work. Each period, the contractor fills in the G703 for every line: the value, what was billed before, what was done this period, any stored materials, the total and percent complete, the balance to finish and the retainage. The G702 takes those totals, adds any approved change orders to the contract sum, subtracts retainage and previous payments, and shows the current payment due.
Under the standard AIA general conditions, the schedule of values, unless the architect objects to it, is the basis for reviewing every payment application. That is why a clear, detailed schedule of values at the start makes every pay application easier to review and quicker to pay.
Who certifies it
The G702 works as both the contractor's request and the architect's certification. The contractor signs it; the architect reviews it against what they see on site and the data in the application, then certifies the amount due. The owner pays the certified amount on the schedule the contract sets. On a job without an architect, the owner or the owner's representative does that review.
What an owner should check
- Progress matches the site. A line billed at 60 percent should look about 60 percent done. Walk the job before you approve.
- The contract sum is current. Only approved change orders belong in the net change line.
- Retainage is applied as the contract says. In Oregon and Washington, private-job retainage is capped at five percent of the work completed.
- Stored materials are real. If materials not yet installed are billed, ask where they are and how they are insured.
- Lien waivers come with it. Conditional waivers for this payment and unconditional ones for the last. Our lien waiver guide covers the Oregon and Washington rules.
- The math carries forward. "Previous certificates" should match what you actually approved last time.
At the end of the job
Around substantial completion, the retainage line is often reduced, and the final pay application releases what is left once the punch list is closed and the closeout paperwork, including final lien waivers, is in. The balance to finish then goes to zero. Related terms are in our commercial construction glossary.
Frequently asked questions
What is a pay application in construction?
The contractor's request for a progress payment, usually monthly. It shows the work done to date against the schedule of values, subtracts retainage and earlier payments, and arrives at the amount due. On AIA contracts it is the G702 cover sheet plus the G703 continuation sheet.
What is the AIA G702?
The Application and Certificate for Payment: a one-page summary that serves as both the contractor's request for payment and the architect's certification of the amount due. It takes its totals from the G703.
What is the difference between the G702 and G703?
The G703 lists every line of the schedule of values with its progress and retainage. The G702 totals those lines, adds change orders, subtracts retainage and previous payments, and certifies the payment due. One supports the other.
Who certifies a pay application?
On architect-led jobs, the architect reviews the application against the work on site and certifies the amount due. Without an architect, the owner or the owner's representative does that review.
What should come with a pay application?
Commonly, lien waivers from the contractor and major subcontractors and suppliers, and backup for any stored materials being billed. The contract lists what is required.
The bottom line
A pay application turns progress on site into a payment: the G703 lists the work line by line, the G702 totals it and certifies what is due. Check progress against the site, keep the contract sum current, apply retainage as the contract says, and collect lien waivers with every payment.
Modern Northwest has built everything from the 700 square foot Sit Still Salon in Vancouver to the 5,618 square foot Orenco Family Medicine clinic in Hillsboro, in Oregon and Washington since 2005. Tell us about your project.
Sources
- AIA Contract Documents, G702-1992 Application and Certificate for Payment (form preview, PDF)
- Autodesk Construction Cloud, "A Guide to G702 and G703 Forms in AIA Billing"
- Corpay, "Schedule of Values in Construction: A Pay-Application Playbook"
- AIA Contract Documents, "What is a Schedule of Values and Why is it Important to a Contractor?"
Starting a commercial project?
Tell us about it. We will show you how billing, retainage and closeout will work before you sign.
Request a Free Consultation